October 2023
5 Months

In this comprehensive project, we upgraded the existing Pre-hop and Hop Dosing Tank Systems across four plants. Our scope of work included the procurement of spare parts, system design, panel assembly, and commissioning. This upgrade improved the precision and efficiency of the hop dosing process, crucial for maintaining product quality and consistency in beverage production.

Operations Performed

  • Upgrade of the existing Pre-hop and hop Dosing Tank System across four plants, including procurement of spares, design, panel assembling, and commissioning.